2.2. EDACS HARDWARE REQUIREMENTS
Jessica requires the EDACS hardware revision levels shown below to support the software revision levels presented in
the preceding section.
2.2.1. System Manager Requirements
Hardware Hardware Revision
PDP System Manager NA
VAX System Manager NA
2.2.2. Site Controller Requirements
Hardware Hardware Revision
VAX Site Controller 19A149302P8 for Europe
19A149302P5 for US
The PDP Site Controller does not support Jessica.
2.2.3. IMC Requirements
Hardware Hardware Revision
Controller Board Rev. G or later for 19D903299P1 on all but the PIM
or
any rev. for 19D903299P3 on all including the PIM
Audio Board Rev. H or later for 19D903302P1
or
any rev. for 19D903302P3
Clock Board Rev. E or later
N. America may use Rev. D or later
MOM PC NA
2.2.4. GETC Requirements
The following three GETC categories differ in that not all use the Turbo option, and the three do not share common
software.
2.2.4.1. GETC 1-E Control/Working Channel Requirements
Hardware Turbo Hardware Revision
Control/Working Channel Yes Rev. F or later for 19D902104
or
any rev. of 19D904266